If your building is older than 60 years, you need a heritage permit before you alter or demolish it. noh ARCHITECTS prepares heritage permit applications for owners in Gqeberha (Port Elizabeth) and across Nelson Mandela Bay, and we have done so for more than twenty years. This page sets out who needs a permit, what we do, the jobs we have done and the questions owners ask us most.
Who needs a heritage permit?
Section 34 of the National Heritage Resources Act says that no one may alter or demolish a structure, or part of a structure, that is older than 60 years without a permit from the provincial heritage resources authority. In the Eastern Cape that is ECPHRA, the Eastern Cape Provincial Heritage Resources Authority.
The rule covers every building older than 60 years, not only declared heritage sites. The cut-off moves forward every year, so a building that didn’t need a permit a few years ago may need one now.
“Alter” is wider than most people expect. The Act counts any work that changes a building’s structure, appearance or physical properties, including painting and plastering. Additions, new windows and doors, a new roof, taking out walls and partial demolition all count.
Owners in the older parts of the city run into this all the time: Walmer, Central, Richmond Hill, Mill Park and the other older suburbs of Gqeberha, as well as Kariega (Uitenhage).
What we do
We look after the whole application, from the first question through to plan approval.
- Do you need a permit? We work out the age of the building from the approved plans, the survey diagram and other records, and tell you whether ECPHRA needs to see your proposal.
- Drawings and photographs. We measure the building and prepare coloured-up drawings of what is there and what is proposed, with a locality plan, a site plan and labelled photographs of the building and its street.
- History and motivation. We write up the history of the property and the motivation for the work: why it is needed, and how it respects what matters about the building.
- The ECPHRA application. We complete the application form, gather the documents ECPHRA asks for, consult heritage organisations and neighbours where needed, and lodge the application.
- Follow-up to plan approval. We answer the committee’s questions, revise the drawings if asked, and carry the permit through to building plan approval at the municipality.
A heritage permit does not replace building plan approval. You need both, and we look after both.
Our track record
Some of the heritage permit applications and old-building projects we have worked on:
Aberdeen’s Building, Central (2025)
Conversion of the building to student accommodation. Heritage permit application prepared.
Gamble Street Secondary School, Kariega (2012 and 2024)
Alteration and restoration of the school buildings for the Independent Development Trust. Heritage permit applications prepared.
Newspaper House, Central (2021)
Alterations to turn the former home of The Herald into student accommodation and offices. Heritage permit application prepared.
Our former offices, Walmer (2019)
Heritage permit application prepared.
Building in Mill Park
Heritage permit and demolition permit applications prepared.
Farm cottage and shop, Pebblespring Farm, Kragga Kamma Road (2013)
Emergency repairs to the farm’s old homestead cottage and its shop: brickwork, plaster, roofs, doors, windows and floors. Heritage permit application prepared.
Magistrate’s Court, Qonce (King William’s Town)
Heritage permit application prepared for the national Department of Public Works.
St Dominic’s Priory, Miramar (2009)
Alterations and additions to the convent. Heritage permit application prepared. We have also worked on the priory’s grotto and its pre-primary school.
North End Prison, Gqeberha
Refurbishment of the prison, as part of the consortium appointed for the revamp. Heritage permit application prepared.
215 Govan Mbeki Avenue, Central (2007)
Heritage permit application prepared.
Brookes Hill Fort (2003)
A World War II-era lookout post of free-form concrete, with interesting camouflage, looking out over Algoa Bay. Heritage permit application prepared.
Where we work
We prepare heritage permit applications throughout Nelson Mandela Bay: Gqeberha (Port Elizabeth), Kariega (Uitenhage) and Despatch. We have also worked further afield in the Eastern Cape, such as on the Magistrate’s Court in Qonce. Our office is at 55 Richmond Hill Street, Richmond Hill, Gqeberha.
Questions owners ask
My house isn’t a declared heritage site. Do I still need a permit?
Yes, if it is older than 60 years. Section 34 applies to every structure older than 60 years, whether or not it has ever been declared.
How do I find out how old my building is?
Approved plans held by the municipality are the best evidence. Where there are none, the survey diagram shows the earliest date the building could have been put up. We explain how in How to Determine the Age of a Building, or we can check for you.
Does painting or a new window count?
It can. The Act’s definition of altering includes painting, plastering and decoration as well as building work. If you’re not sure, ask before you start.
Do I still need my building plans approved?
Yes. A heritage permit doesn’t replace municipal approval. You need both, and we usually get the heritage permit in place first.
What does it cost?
ECPHRA charges an application fee for built environment applications: R1 000 since June 2023. Our own fee depends on the building and the work, and we’ll quote once we have seen it.
How long does it take?
ECPHRA’s committee meets on a fixed schedule, and an application must be in at least two weeks before a meeting. The committee may come back with questions, so allow time for a second round. We’ll give you a realistic timeline once we know the building.
Do I need a heritage permit to demolish?
Yes. Demolishing all or part of a structure older than 60 years needs a heritage permit, and in Nelson Mandela Bay you need it before you apply to the municipality to demolish. See Yes, You Need a Permit to Demolish a Building Too.
The work has already started. Can we apply now?
Talk to us straight away. ECPHRA does not issue permits after the fact, and work done without a permit breaks the law. It is always better to apply before you start.